JEFFCO BUILDS ARTICULATION AREAS - GREEN MOUNTAIN

Thank you Jeffco Voters for making the choice to support our schools.

Jeffco Public Schools is divided into 17 areas providing assigned schools for each neighborhood served as well as option and charter school choices

JEFFCO BUILDS ARTICULATION AREAS - GREEN MOUNTAIN

IN CONSTRUCTION

Large build projects (building additions, rebuilds, etc.) are currently under construction.

COMPLETE

Projects are complete.

IN DESIGN

Projects are currently being designed by architecture and construction partners.

PARTIALLY COMPLETE

Smaller projects that have partially completed their list of improvements.

School Improvements
Devinny Elementary
  • Remove modular buildings
  • Security camera & lock updates
  • Secure entries & office locations
  • Update existing technology
  • Update electrical wiring & increase capacity
  • Commercial kitchen improvements
  • Parking lot & sidewalk improvements
  • Replace old playground equipment
  • Replace old furniture
  • Replace old carpet & floor tile
  • Replace moveable partitions
  • Replace old sinks, cabinets & shelving
  • Replace interior lighting with LEDs

Estimated project timeline: Sept. 2020 - Oct. 2021

 
Dunstan Middle



  • Security camera & lock updates
  • Secure entries & office locations
  • Update existing technology
  • Update electrical wiring & increase capacity
  • Update HVAC, plumbing & piping
  • Replace interior lighting with LEDs

Estimated project timeline: Sept. 2022 - Oct. 2023

Foothills Elementary



  • Remove modular buildings
  • Security camera & lock updates
  • Secure entries & office locations
  • Update existing technology
  • Update interior paint, wall-coverings
  • Update electrical wiring & increase capacity
  • Update HVAC, plumbing & piping
  • Commercial kitchen improvements
  • Replace old furniture
  • Replace moveable partitions
  • Replace old sinks, cabinets & shelving
  • Replace interior lighting with LEDs
  • Replace old ceilings

Estimated project timeline: Sept. 2019 - Oct. 2020 

Green Mountain Elementary


  • Security camera & lock updates
  • Secure entries & office locations
  • Update existing technology
  • Update interior paint, wall-coverings
  • Update electrical wiring & increase capacity
  • Update HVAC, plumbing & piping
  • Commercial kitchen improvement
  • Replace old carpet & floor tile
  • Replace moveable partitions
  • Replace old sinks, cabinets & shelving
  • Replace interior lighting with LEDs
  • Replace old ceilings
  • Replace worn roofing 

Estimated project timeline: Sept. 2021 - Oct. 2022

Green Mountain High 


  • Expand with addition
  • Remodel building interior
  • Remove modular buildings
  • Security camera & lock updates
  • Secure entries & office locations
  • New, more secure doors
  • Update existing technology
  • Landscaping & field improvements
  • Update interior paint, wall-coverings
  • Update electrical wiring & increase capacity
  • Update HVAC, plumbing & piping
  • Update caulking, trim & window sills
  • Repair & update exterior finish 
  • New paint to protect exterior 
  • Commercial kitchen improvements
  • Parking lot & sidewalk improvements
  • Replace old furniture
  • Replace old carpet & floor tile
  • Replace old sinks, cabinets & shelving
  • Replace interior lighting with LEDs
  • Replace old ceilings

Hutchinson Elementary


  • Remove modular buildings
  • Security camera & lock updates
  • Secure entries & office locations
  • Update existing technology
  • Landscaping & field improvements
  • Update electrical wiring & increase capacity
  • Update HVAC, plumbing & piping
  • Commercial kitchen improvements
  • Replace old playground equipment
  • Replace old furniture
  • Replace old carpet & floor tile
  • Replace moveable partitions
  • Replace old sinks, cabinets & shelving
  • Replace interior lighting with LEDs

Estimated project timeline: Sept. 2019 - Oct. 2020
 
 Rooney Ranch Elementary
  • Remove modular buildings
  • Security camera & lock updates
  • Secure entries & office locations
  • Update existing technology
  • Update electrical wiring & increase capacity
  • Update HVAC, plumbing & piping
  • Replace old carpet & floor tile
  • Replace moveable partitions
  • Replace old sinks, cabinets & shelving
  • Replace interior lighting with LEDs
Estimated project timeline: Sept. 2023 - Oct. 2024

Estimated cost of proposed improvements subject to change per final project scope. Estimated project time line subject to change.